Trade show planning timeline from booth space to ship date

Flat illustration of two workers loading booth crates onto a box truck at a workshop loading dock, one crate red

Plan your trade show around two dates: the day you book your booth space, and the day your booth ships. At large shows, booking for the best space happens 7 to 10 months before opening. Your booth ships much later. Freight usually has to reach the show’s warehouse 11 to 13 days before opening, so your booth leaves earlier still, once you allow for the trip.

Everything about the booth has to be finished by that ship date, graphics included. How early the work starts is set by the kind of booth you want:

  • Custom booth: design and production take us 8 to 15 weeks. If your booth ships 3 weeks before the show, design has to start 11 to 18 weeks before opening, at the latest.
  • Rental from our inventory: often possible on short notice, because the structure is already built.
  • Refresh of a booth you own: the structure already exists, so the time goes to repairs, replacement parts and new graphics. Order new graphics at least 2 to 4 weeks before the show.

At Xibit Solutions, we’ve designed, built and installed booths for shows across the country for over 20 years, and these are our own build times.

Trade show timeline at a glance

Many of a show’s deadlines come from its general service contractor, the company the show hires to run freight, installation labor and services such as electrical and furniture. That contractor also runs the advance warehouse, which collects exhibitors’ crates in the weeks before the show and delivers them to each booth at move-in.

The show deadlines in this table are ranges from the published exhibitor calendars of several large shows, counted back from opening day. For the booth work, the table uses an example ship date 3 weeks before opening. Swap in your own ship date once you know it. Candy Adams, an independent exhibit-management consultant who writes for EXHIBITOR magazine, says there are “far too many variables” for a generic timeline to be useful when building a new exhibit. Use these ranges to plan, then replace them with your show’s dates and your builder’s schedule as soon as you have them.

Before the show opensWhat happensWho does it
7 to 10 monthsThe first round of booth space booking. At some shows, returning exhibitors pick first.You
As soon as you know your show dates and booth sizeCall your booth builder.You
Several months aheadThe exhibitor manual comes out with the show’s deadlines.You and us
11 to 18 weeks at the latest, with a 3-week ship dateCustom booth design starts.You and us
6 to 14 weeksDrawings of larger booths and hanging signs go to the show for review.Us, when we install your booth
About 5 to 7 weeks, with a 3-week ship dateFinal artwork is due for graphics that ship with your booth.You approve it, we print it
3 to 5 weeksLast day for discounted rates on show services such as electrical, furniture and laborUs, for the services we order for you; you, for the rest
10 days to 6 weeksThe show needs a form naming your installer, if it isn’t the general service contractor.Us, when we install your booth
3 weeks in this exampleYour booth ships.Us
Less than 3 weeksRental orders placed now typically carry rush charges.You
6 to 13 daysLast day for freight to reach the advance warehouse without a surchargeUs, when we ship your booth
5 to 7 daysMove-in begins. A custom booth takes 1 to 3 days to install.Us, when we install your booth

Travel, booth staffing and pre-show marketing run alongside all of this, and our guide for first-time exhibitors covers them.

When to book booth space

Book your space as soon as you’ve decided to exhibit. The space sets your booth’s size and its spot on the floor, and a builder can’t start designing until both are known.

Large shows often book space in rounds, and the first round gets first choice of location. At IPPE 2027 (the International Production & Processing Expo), returning exhibitors began choosing space about 9 months before the show, in order of how many years in a row they’d exhibited. New exhibitors could book from about 7.5 months out.

Adams has also written in EXHIBITOR that “Some shows start their space sign-ups before the previous year’s show even opens.” If you want a particular location, ask the show now when booking opens for the show you’re planning.

When does your booth need to ship?

Your ship date is the show’s freight deadline, minus the time your freight spends in transit, minus a little cushion. Say freight has to reach the advance warehouse 12 days before opening, the trip takes a week, and you allow a couple of days of cushion. Your booth then ships about 3 weeks before the show, which is where the table’s 3-week example comes from.

If your booth goes to the advance warehouse, the warehouse typically starts taking freight 1 to 2 months before the show. The last day to arrive without a surcharge is usually 11 to 13 days before opening, though one show set it at 6 days. The other route is to ship straight to the convention center, which typically accepts freight from about 5 to 7 days before opening, when move-in begins. Our trade show logistics guide covers carriers, crating and the warehouse in more detail.

When to book a booth builder

Call a builder as soon as you know your show dates and roughly what size booth you’ll have. The latest you can call is set by the booth: its type, its size and whether you’re starting from scratch. If you’re still choosing a builder, our guide on how to evaluate and choose a trade show exhibit company covers what to ask.

How long a custom booth takes

A custom booth goes through four stages with us:

  1. Consultation. One or two meetings about your goals, your audience, your budget and the venue’s requirements.
  2. Design concepts, about 2 to 3 weeks. You see 3D renderings and floor plans, go through revisions, and approve the booth visually before anything is built.
  3. Detailed planning and prototyping, about 2 to 4 weeks.
  4. Production, about 4 to 8 weeks, with complex booths at the longer end.

Installation at the show then takes 1 to 3 days.

Added up, design and production take 8 to 15 weeks. Production has to end by your ship date, so if your booth ships 3 weeks before the show, design concepts have to start 11 to 18 weeks before opening. The consultation comes before that. These are typical estimates, and a complex booth or a late decision can stretch them. A design that’s still changing holds up every stage after it, so decide early where you can.

That’s the latest you can start. We’d rather start months earlier: for a show at the end of September 2027, our PACK EXPO Las Vegas guide recommends starting booth design in early 2027. The extra time covers revisions, your company’s own approvals, and any show deadlines that fall before production starts.

Does a bigger booth need more time?

A bigger booth needs an earlier start. As Adams writes, “The larger the exhibit, the more time it will take to design and fabricate.”

Large booths also have an extra show deadline. The show reviews drawings of larger booths and hanging signs before move-in, and those drawings are typically due 6 to 14 weeks before opening. Each show sets its own size limit, for example:

  • IPPE 2027: layouts for peninsula booths (open on three sides) and island booths (open on all four) of 300 square feet or more
  • NAB Show 2026: a booth review form for booths of 800 square feet or more
  • SEMA Show 2026: a booth design notice for booths 20’x20′ or larger

A standard 10’x10′ or 10’x20′ inline booth is under all three limits.

For a large booth, the drawing deadline can come before production would even start. If your booth ships 3 weeks before the show, production starts 7 to 11 weeks before opening, and a drawing deadline can fall as early as 14 weeks out. Find out what your show asks for and when it’s due, and plan the start of design so the drawings are ready in time. If you’re planning an island, a two-story booth or a hanging sign, look up this deadline first.

How much time a rental booth needs

A rental needs less lead time than a custom build. Can we handle a last-minute rental? Often, yes. Our rental structures are already built, so the work is mostly planning your layout, printing your graphics in our own shop and scheduling installation.

Calling early still helps. Rental orders placed less than 3 weeks before the show typically carry rush charges, and what we can offer depends on what’s in our inventory at the time. A rental with custom elements also needs design time first, so call earlier for one of those. If you’re still deciding between renting and buying, our article on whether to rent or purchase a booth walks through that choice.

How much time a booth refresh needs

A booth you own skips the build, so the time before it ships goes to whatever work it needs. We handle touch-up painting, structural repair, replacement of worn components, electrical and lighting testing, and graphic updates. An owned booth can also be reconfigured for a different footprint, such as taking a 20’x20′ modular structure down to fit a 10’x20′ space.

If it only needs new graphics, order them at least 2 to 4 weeks before the show, and earlier if they ship with the booth. Repairs, replacement parts or a new layout add design and shop time. Have the booth checked as soon as you know the show, so you find any damage while there’s still time to fix it.

When to order and approve graphics

Order graphics at least 2 to 4 weeks before your show to allow time for proofing, revisions and production. Custom or specialty prints may need more time. Graphics that ship with your booth have to be finished before it leaves, so count those weeks back from your ship date instead. With the 3-week example ship date, your final artwork would be due roughly 5 to 7 weeks before opening. Leave time before that for your own team to sign off. Because we print in our own shop, there’s no back-and-forth with an outside printer, and that tends to keep the time shorter.

Graphics you order from the show’s general service contractor have their own order deadline, typically about 3.5 to 6.5 weeks before opening.

Our guide to trade show graphics and large-format printing goes into materials and printing in more detail.

The exhibitor manual and show service deadlines

The exhibitor manual, which some shows call the exhibitor services manual or show kit, comes out months before the show: about 4 months ahead at the AAOS Annual Meeting and about 5.5 at IPPE. When you get it, copy every deadline into your calendar and set your own date a week earlier. Adams does the same: “I fudge my deadlines by a week, especially if a discount is offered.” A week of cushion means one slow approval on your side doesn’t cost you a discount.

When we install your booth, we handle many of those deadlines for you. We submit the show’s forms and paperwork on your behalf, schedule the advance warehouse delivery, and handle rigging requests and engineering documents for hanging signs. We can also place your electrical and internet orders. That leaves you the space contract, your design and artwork approvals, and any show services we aren’t ordering for you.

Discount deadline for show services

Show services are what you order from the general service contractor for your booth space, such as electrical, furniture, carpet, cleaning, internet and labor. They cost less if you order by the discount deadline, which typically falls 3 to 5 weeks before opening.

Form for your own installer (EAC)

The general service contractor supplies installation labor, but you can bring in another company instead, such as your builder. The show calls that company an exhibitor-appointed contractor (EAC) and needs a form naming it, usually with proof of insurance. The deadline ranges from 10 days to 6 weeks before opening, so check your show’s manual for the date.

What happens if you miss a deadline?

Most missed deadlines cost money. At IBIE 2025 (the International Baking Industry Exposition), the electrical order forms carried this note: “Subject to 50% charge for orders after the deadline.” Artwork or booth decisions that reach a builder or printer late can bring rush charges too. Adams’ advice: “Be sure to ask when rush charges, which can double your bill, will go into effect, and add these dates to your pre-show timeline.”

If you miss a drawing deadline or the installer form, call show management right away and ask what they can still accept. Our article on the hidden costs of trade show exhibiting covers late charges and the rest of the show budget.

Short on time? What’s still possible

If your show is close, first check which deadlines have already passed. Then pick the booth that fits the time you have left.

Less than 3 months out

With 3 months to go, a new custom build only works if it’s simple. If your booth ships 3 weeks before the show, that leaves about 10 weeks for design and production. That covers only the short end of our 8 to 15 weeks, and only if decisions come fast. A rental with your own graphics, or a refresh of a booth you own, is the safer choice. If your booth is big enough to need drawings, check that deadline first, because it may be only a few weeks away or already past.

Less than 6 weeks out

With less than 6 weeks to go, a new custom build won’t fit, because our typical design and production time starts at 8 weeks. Choose a rental from our inventory, or refresh a booth you own with new graphics. Get your artwork final now, since graphics need to be ordered at least 2 to 4 weeks before the show, and earlier if they ship with your booth. The discount deadline for show services typically falls 3 to 5 weeks before opening, so place those orders this week.

Less than 3 weeks out

With less than 3 weeks to go, a rental from our inventory is often still possible, but expect rush charges. Rush graphics orders are sometimes possible, though proofing and revisions still take time. The advance warehouse may stop taking freight within days, so ask your builder whether the booth should go there or straight to the show. Most discount deadlines for show services will have passed, so expect those services to cost more.

Let’s discuss your upcoming show

We design, build and print graphics in our North Las Vegas facility, and we manage the installation at the show, so you have one company to call for all of it. Send us your show date, your booth size and the kind of booth you want: a custom build, a rental or a refresh. We’ll work back from your ship date with you and set a start date for each piece. Contact us today at (702) 361-7502 to get your free estimate.

Free Quote
Planning your next trade show?

Custom booths, rentals, graphics, shipping and on-site setup, handled by one team since 2001.

In this article

Keep Reading

More trade show guides

Ready to stand out at your next show?

Tell us about your next show. We design, build, ship and install exhibits that get your brand noticed on the floor.